Quality of Materials Delay Asphalt Of Road To Monteverde

The road construction to Monteverde, between Guacimal and Santa Elena, has suffered another setback, the asphalting will no longer be ready in September as promised by the previous administration.
The completion of the road to Monteverde had been promised for Christmas
The fear of the residents is that they will not have the road by Christmas as promised by the government of Luis Guillermo that began the work to this important tourist area, that was stalled from almost a decade.
In addition, they are concerned about the quality of the work.
The new concerns originated with a report from the National Laboratory of Materials and Structural Models (Lanamme) of the University of Costa Rica, according to which the material that used in the sub-base of the pavement does not

... continue reading article at QCOSTARICA.com Click here to go to the source article.

Written by Q COSTARICA

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

Loading…

0

Government of Luis Guillermo Solís disguised the real size of the country’s debt for 2018

Costa Rica Rocks: A night of heavy metal in Cartago